Valley Mall BLVD Construction, Yakima, WA

Valley Mall Blvd

The Valley Mall Blvd. Interchange project was a WSDOT public works contract that made provisions of the improvement of traffic flow on I-82 and Valley Mall Blvd. utilizing 3 new roundabouts and 2 new structural concrete bridges.  The $24 million dollar contract spanned over 18 months and improved roughly 5 miles of road in Yakima County and the City of Union Gap.   The interchanges were constructed of using a series of cast in place roundabouts and required that our crews work under traffic to complete the extensive utility relocation and road widening of Valley Mall Blvd.

Apollo Inc, self performed all mass excavation, structural concrete, bridge construction and underground utility work on the project.