removal of the preload material on the existing site
excavation for eleven new structures and associated dewatering
underground process piping and structure under drainage system
construction of 1 concrete selector tank structure, 2 concrete clarifier structures, 1 concrete re-aeration basin structure
1 influent pump station, 1 UV/RAS building, 1 pretreatment building, and 1 head works building
supply and installation of process equipment, electircal and controls, site improvments, untility and raod improvemnts
40 acres of lagoon modificaitons
![]() |
![]() |